A planned nuclear-powered supercomputing hub in the Texas Panhandle has cleared a major federal regulatory hurdle.
The US Nuclear Regulatory Commission (NRC) has published its draft environmental review for Project Matador, an energy and artificial intelligence campus run by developer Fermi America. Crucially, NRC staff issued a preliminary recommendation to approve combined licenses for four Westinghouse AP1000 nuclear reactors, provided the project passes an ongoing safety evaluation.
The positive assessment arrived just 15 months after Fermi America filed its application. In the nuclear industry, federal environmental reviews typically take years to complete. Reaching this stage so quickly marks significant momentum for an initiative designed to power high-demand computing facilities.
Proposing a new power outlook
With Project Matador, the overall technology infrastructure could get a new outlook. It does not rely solely on the public grid. Instead, Fermi America is building a dedicated private system in Carson County, near Amarillo. The private network will combine commercial nuclear reactors with natural gas units, solar arrays, and utility-scale battery storage.
Original plans for the site called for an 11-gigawatt (GW) campus, anchored by 4.4 GW of nuclear power. However, developers recently expanded their ambitions to nearly 17 GW. The upgrade aims to meet the relentless power appetite of next-generation artificial intelligence models and high-performance computing clusters, which require round-the-clock baseload electricity that intermittent renewables cannot supply alone.
The site is being developed across 18 million square feet in partnership with Texas Tech University. Construction is scheduled to bring the facility online in stages, starting in the late 2020s and running into the mid-2030s.
The federal recommendation builds directly on state-level regulatory wins from earlier this year. In February, Texas environmental authorities granted Project Matador a six-gigawatt Clean Air Permit. That decision stands as the second-largest air permit in US history, paving the way for the fossil fuel generation that will support the campus alongside its planned reactors.
Clearing crucial regulatory hurdles
Despite the recent progress, several crucial regulatory steps remain before safety-related construction on the nuclear reactors can begin. The NRC must complete and publish its final environmental impact statement.
Simultaneously, regulators must complete a Safety Evaluation Report to verify that the standardized AP1000 design is compatible with the local geology, seismic conditions, and water resources. Only after both reviews conclude will the full Commission hold a vote on final license approval.
Fermi America is advancing the complex design with several engineering and nuclear partners. The coalition includes reactor designer Westinghouse Electric Company, Hyundai Engineering & Construction, ENERCON, and Preferred Licensing Services.
Largest private energy installations
The project’s nuclear division is led by Mesut Uzman, alongside development leads Sezin Uzman, Andrew Bryant, and Dannie Weaver. If the remaining approvals follow smoothly, Project Matador will stand as one of the largest private energy installations in the world.
It aims to bridge conventional nuclear engineering with the expanding power demands of the digital economy.
“As Project Matador continues to advance, Fermi America remains focused on progressing through the remaining regulatory milestones and developing the energy infrastructure needed to power America’s AI future,” concluded the company.