KUALA LUMPUR: Jati Tinggi Group Bhd has secured a RM30.1 million contract to undertake power infrastructure works for a data centre in Kulai, Johor.
In a filing with Bursa Malaysia, Jati Tinggi said its unit, Jati Tinggi Holding Sdn Bhd, accepted the letter of acceptance from an unnamed customer on Oct 16.
The customer is a Malaysian company involved in providing infrastructure for hosting, data processing services and related activities.
The contract covers the design, engineering, procurement, construction and commissioning of two circuits of 275-kilovolt (kV) underground cable ducting, cable pits and 11kV temporary power interconnection works.
The scope also includes authority submissions, supply, delivery, installation, testing and commissioning, as well as support and maintenance during the defects notification period.
The contract is effective from the date of acceptance until July 25, 2027.
"The letter of award is expected to contribute positively to the future earnings, earnings per share and net assets per share of the company over the duration of the contract," it said.