Two EU regulations will require ports to provide shore power and ships to use it from 2030. But with grid upgrades taking up to a decade, the infrastructure needed to meet the deadline is struggling to keep pace. Alex Byelyavtsev reports.
By 2030 two EU rules meet at the quay. AFIR tells TEN-T core and comprehensive ports above a traffic threshold, not only the big hubs, to put shore power on the berth for 90% of qualifying container and passenger calls. FuelEU Maritime tells those ships, if they stay more than two hours, to connect and take their electrical load from it. One rule builds the socket. The other requires the ship to plug into it. The date, from Fit for 55, is already doing the ordering. It is not building the grid.
On the ship the box can be bought. In July 2026 Cavotec took an order to retrofit containerships with a containerised cable system while they stay in service. DNV had about 20% of world containerships equipped with a shore-power connection. Hapag-Lloyd is further along, about 35%. A company can fit a ship. FuelEU still names that company even when the quay has no live point, or a charter ship has no socket.
In the port the iron is thinner. Transport & Environment, from DNV, put guaranteed container connections at about 11% of what 31 European ports need by 2030. Much of the OPS already advertised is low voltage. Deepsea boxes need high voltage. The 90% test is still ahead of the cable.
The calendar does not match. From October 2026 to 31 December 2029 is a little over three years. ESPO, setting out the commission’s grid-connection guidance, puts extra grid build at four to ten years, against two to three for the port-side connection. If the request is not already in the queue, parts of the required build may not fit the time left. Rotterdam is aiming for the second half of 2028. ABB says that kit is meant to supply up to 32 containerships at once. The port’s own strategy still records grid congestion. Installed megawatts are not the event the grid sees. The event is coincidence. A 90% coverage test does not ask whether those megawatts are free at 07:00 on a Saturday.
The clock starts when the ship is alongside, not when the cable is live. Hamburg’s routine connection is about an hour to an hour and a half. If the commercial berth has no socket, the stay can still be a FuelEU call of more than two hours.
What a master can do is ask before arrival. Article 6 already lists the misses: no point, not enough power or grid stability, incompatibility on a certified ship installation, emergency. From 1 January 2035 those availability exceptions tighten to the lower of 10% of a ship’s annual calls or ten calls, unless the company shows it could not reasonably have known. That showing sits on the information exchanged before entry. A dead cabinet is a legal category. After 2035 an unasked miss can become a counted one, and a FuelEU penalty on the electricity that should have come from shore. That is not a hole found later. It is how a duty stays on the books when the connection cannot. IMO 2020 did not need that. A 0.50% fuel could be blended. A substation cannot.
The bill is separate. A parliament study759345) finds the EU can mandate the socket and still have no common price rule. Under the Energy Taxation Directive, electricity produced on board at berth must be exempt. Shore-side electricity is not covered by that exemption. A member state needs a Council authorisation to apply a reduced rate. Germany obtained one in June 2026, through 31 December 2029. In tramp trades the OPS invoice may not follow the bunker. The visible shore bill is still stacked against the auxiliary engines.
There is no sign of a general 2030 delay. If the megawatts, the berth and the cable are there, the auxiliaries stop. If they are not, the ship stays on its own plant and the call sits on the exception list. Article 6 already holds those misses. AFIR is due a review by 31 December 2026. A date that cannot be followed as written is then followed through exceptions, then through reviews. A date can mandate a connection. It cannot manufacture grid capacity. The plug is not the power.
Splash
Splash is Asia Shipping Media’s flagship title offering timely, informed and global news from the maritime industry 24/7.
Newsletter
Read Next
October 13, 2026
Britain urges ships to prepare for life without reliable GPS
October 12, 2026
Danaos and Cetus push dry bulk listing plans in Oslo
October 12, 2026
Baltic states push for EU-wide ban on Russian grain transit
October 12, 2026